Roof replacement and slope correction
Federal contribution
$305,183
Federal share80%
of $381.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de la Montérégie-Centre
- Construction start
- Oct 27, 2021(actual)
- Construction end
- Aug 15, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast May 31, 2022