Back to projects

Replacement of Washrooms in Wings G and H

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$907,700
Federal share45%

of $2.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Collège Dawson
Construction start
Jun 3, 2021(actual)
Construction end
Dec 15, 2021(actual)

Also in Montréal