Roof repair of the Wing J
Federal contribution
$350,000
Federal share70%
of $500.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège Dawson
- Construction start
- May 16, 2022(actual)
- Construction end
- Oct 19, 2022(actual)
Against the original forecast
- Construction start6 weeks lateforecast Apr 4, 2022
- Construction end8 weeks earlyforecast Dec 14, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59145 in the federal list. How to read these figures.