Roof repair of the Wing J

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$350,000
Federal share70%

of $500.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Collège Dawson
Construction start
May 16, 2022(actual)
Construction end
Oct 19, 2022(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Apr 4, 2022
  • Construction end8 weeks earlyforecast Dec 14, 2022

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59145 in the federal list. How to read these figures.