Repointing the stones of the main entrance
Federal contribution
$530,000
Federal share71%
of $750.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège Dawson
- Construction start
- Jun 1, 2022(actual)
- Construction end
- Feb 16, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Dec 14, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59146 in the federal list. How to read these figures.