Asbestos Encapsulation and Removal Work
Federal contribution
$729,793
Federal share80%
of $912.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Cégep Édouard-Montpetit
- Construction start
- Jun 1, 2023(actual)
- Construction end
- Jun 22, 2024(actual)
Against the original forecast
- Construction end8 weeks earlyforecast Aug 19, 2024
Also in Longueuil
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59147 in the federal list. How to read these figures.