Replacement of heat pumps
Federal contribution
$168,831
Federal share80%
of $211.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège Héritage
- Construction start
- Jul 1, 2021(actual)
- Construction end
- Nov 1, 2023(actual)
Against the original forecast
- Construction end6 months lateforecast Apr 19, 2023