Replacement of the IT campus elevator
Federal contribution
$142,500
Federal share43%
of $328.6K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- O'Sullivan College of Quebec
- Construction start
- Apr 24, 2021(actual)
- Construction end
- Jan 31, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Nov 30, 2021
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59163 in the federal list. How to read these figures.