Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 24, 2021(actual)
Construction end
Jan 31, 2022(actual)

Against the original forecast

  • Construction end2 months lateforecast Nov 30, 2021