Outdoor renovation

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$12,000
Federal share70%

of $17.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
École nationale de cirque
Construction start
Jul 7, 2022(actual)
Construction end
Sep 29, 2023(actual)

Against the original forecast

  • Construction start10 months earlyforecast May 1, 2023
  • Construction end2 months lateforecast Jul 17, 2023

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59165 in the federal list. How to read these figures.