Integrated equipment upgrade
Federal contribution
$38,154
Federal share51%
of $74.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- École nationale de cirque
- Construction start
- Jul 15, 2021(actual)
- Construction end
- Nov 15, 2021(actual)
Against the original forecast
- Construction end3 months lateforecast Aug 20, 2021
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59166 in the federal list. How to read these figures.