Replacing the server room air conditioning system
Federal contribution
$225,000
Federal share69%
of $327.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- École nationale d'administration publique
- Construction start
- Mar 1, 2022(actual)
- Construction end
- Apr 29, 2022(actual)