Replacement of the fire protection system
Federal contribution
$680,000
Federal share38%
of $1.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège Ahuntsic
- Construction start
- Jun 10, 2021(actual)
- Construction end
- Jun 26, 2024(actual)