Back to projects

Replacement of the fire protection system

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$680,000
Federal share38%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Collège Ahuntsic
Construction start
Jun 10, 2021(actual)
Construction end
Jun 26, 2024(actual)