Repair of a retaining wall and a sorting island in blocks C and A
Federal contribution
$1.4M
$1,376,000
Federal share80%
of $1.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège Ahuntsic
- Construction start
- Apr 23, 2021(actual)
- Construction end
- Dec 31, 2022(actual)
Against the original forecast
- Construction end2 months earlyforecast Mar 16, 2023
Also in Montréal