completeEducation, Training and ChildcareCVRIS
Federal contribution
$508,767
Federal share69%

of $736.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep André-Laurendeau
Construction start
Sep 13, 2021(actual)
Construction end
Dec 15, 2021(actual)