Back to projects

Replacement of windows on the ground floor

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$366,400
Federal share70%

of $525.8K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Cégep André-Laurendeau
Construction start
May 13, 2021(actual)
Construction end
Dec 31, 2021(actual)