Upgrading and repair of the security system and optimization of mechanical systems
Federal contribution
$1.2M
$1,163,081
Federal share80%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Collège LaSalle
- Construction start
- Dec 1, 2022(actual)
- Construction end
- Dec 1, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Sep 30, 2023
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59180 in the federal list. How to read these figures.