Schedule

Announced and approvedJul 8, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Collège LaSalle
Construction start
Dec 1, 2022(actual)
Construction end
Dec 1, 2023(actual)

Against the original forecast

  • Construction end2 months lateforecast Sep 30, 2023