Upgrade of the electrical substation
Federal contribution
$794,858
Federal share76%
of $1.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- École des Hautes Études Commerciales de Montréal
- Construction start
- Jun 28, 2021(actual)
- Construction end
- Apr 20, 2023(actual)
Against the original forecast
- Construction end4 months lateforecast Dec 31, 2022