Centre hospitalier de l'Université Laval (CHUL)'s pharmacy first doses sector retrofit
Federal contribution
$260,000
Federal share80%
of $325.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- CHU de Québec - Université Laval
- Construction start
- Aug 2, 2021(actual)
- Construction end
- Sep 30, 2022(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Aug 16, 2021
- Construction end3 months lateforecast Jun 30, 2022
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59185 in the federal list. How to read these figures.