Interventional Fluoroscopy Room #4 Upgrade at the Centre hospitalier de l'Université de Laval (CHUL)

Québec, Quebec

completeVentilationCVRIS
Federal contribution
$1.2M
$1,238,235
Federal share80%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 7, 2021(actual)
Construction end
Apr 28, 2022(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Aug 21, 2021
  • Construction end3 months earlyforecast Jul 15, 2022

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59186 in the federal list. How to read these figures.