Interventional Fluoroscopy Room #4 Upgrade at the Centre hospitalier de l'Université de Laval (CHUL)
Federal contribution
$1.2M
$1,238,235
Federal share80%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- CHU de Québec - Université Laval
- Construction start
- Sep 7, 2021(actual)
- Construction end
- Apr 28, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Aug 21, 2021
- Construction end3 months earlyforecast Jul 15, 2022