Air Conditioning and Dehumidification Repair at the B Wing care units of the Hôpital Saint-François d'Assise (HSFA)
Federal contribution
$695,884
Federal share80%
of $869.9K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- CHU de Québec - Université Laval
- Construction start
- Aug 1, 2023(actual)
- Construction end
- Mar 31, 2024(actual)
Against the original forecast
- Construction start3 months lateforecast May 1, 2023
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59194 in the federal list. How to read these figures.