Building 350 Roof Repair in the Hôtel-Dieu de Québec (HDQ)
Federal contribution
$143,825
Federal share64%
of $223.8K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- CHU de Québec - Université Laval
- Construction start
- Aug 30, 2022(actual)
- Construction end
- Jul 14, 2023(actual)
Against the original forecast
- Construction end8 months lateforecast Oct 30, 2022
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59196 in the federal list. How to read these figures.