Replacement of boiler # 1

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$512,000
Federal share32%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 18, 2021(actual)
Construction end
May 20, 2022(actual)

Against the original forecast

  • Construction start5 months lateforecast May 31, 2021
  • Construction end4 weeks lateforecast Apr 22, 2022

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59202 in the federal list. How to read these figures.