Modernization and installation of a cart washer and sterilizer (00339)

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$416,000
Federal share80%

of $520.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 25, 2021(actual)
Construction end
Oct 10, 2023(actual)

Against the original forecast

  • Construction end2 weeks earlyforecast Oct 27, 2023