Upgrading of HND laboratory counters (00339)

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$201,822
Federal share80%

of $252.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Dec 15, 2023(actual)

Against the original forecast

  • Construction end3 weeks lateforecast Nov 24, 2023

Also in Montréal