Modernization and optimization of the heating, ventilation and air conditioning (HVAC) system of the bedrooms of the living unit of the 4th West of the IUGM
Federal contribution
$2.4M
$2,400,000
Federal share80%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du Centre-Sud-de-l'Île-de-Montréal
- Construction start
- Oct 19, 2021(actual)
- Construction end
- Dec 15, 2023(actual)
Against the original forecast
- Construction end15 months lateforecast Aug 31, 2022