Teaching and Broadcasting Rooms Upgrade
Federal contribution
$1.1M
$1,130,644
Federal share58%
of $2.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université Laval
- Construction start
- Oct 12, 2021(actual)
- Construction end
- May 4, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Feb 28, 2022
Also in Québec
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59218 in the federal list. How to read these figures.