Energy Network Mechanical Systems Replacement
Federal contribution
$5.9M
$5,935,880
Federal share80%
of $7.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université Laval
- Construction start
- Jan 26, 2023(actual)
- Construction end
- May 30, 2024(actual)