606 and 614 Envelope Renovation at the Faculty of Music
Federal contribution
$931,756
Federal share28%
of $3.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université de Montréal
- Construction start
- Apr 15, 2022(actual)
- Construction end
- Mar 2, 2023(actual)
Against the original forecast
- Construction end2 months lateforecast Dec 31, 2022