Back to projects

Replacement of lighting equipment in sectors C and E

Gatineau, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$660,000
Federal share80%

of $825.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Feb 24, 2022(actual)
Construction end
Apr 30, 2024(actual)

Against the original forecast

  • Construction end4 months earlyforecast Aug 31, 2024

Also in Gatineau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59230 in the federal list. How to read these figures.