Renovation work on the south roof
Federal contribution
$57,800
Federal share74%
of $78.4K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université du Québec - siège social
- Construction start
- May 14, 2022(actual)
- Construction end
- May 27, 2022(actual)
Against the original forecast
- Construction end5 weeks earlyforecast Jun 30, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59232 in the federal list. How to read these figures.