Addition of emergency lighting

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$6,320
Federal share51%

of $12.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 1, 2021(actual)
Construction end
Nov 1, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 1, 2021
  • Construction end2 months earlyforecast Dec 31, 2021