Interior repair (floor, wall, electric baseboard) and exterior (windows, facade, insulation)
Federal contribution
$560,000
Federal share80%
of $700.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré de santé et de services sociaux de Chaudière-Appalaches
- Construction start
- May 1, 2021(actual)
- Construction end
- Dec 2, 2022(actual)
Also in Saint-Flavien
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59250 in the federal list. How to read these figures.