Renovating and upgrading of the generator, electrical distribution and repair of the exterior access

Saint-Flavien, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$320,000
Federal share80%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
May 28, 2021(actual)
Construction end
Nov 1, 2023(actual)

Against the original forecast

  • Construction end4 months lateforecast Jul 4, 2023