Opening of a University Family Medicine Group (GMF-U) on the 2nd floor in front of the existing elevator
Federal contribution
$500,000
Federal share80%
of $625.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux de l'Est-de-l'Île-de-Montréal
- Construction start
- Mar 15, 2021(actual)
- Construction end
- May 17, 2022(actual)
Against the original forecast
- Construction end7 months earlyforecast Dec 24, 2022