Back to projects

Installation of a ventilation unit at the Hôpital Jean-Talon

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$532,000
Federal share80%

of $665.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Nov 1, 2021(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Sep 1, 2021
  • Construction end17 months lateforecast Jul 30, 2022

Also in Montréal