Installation of a ventilation unit at the Hôpital Jean-Talon
Federal contribution
$532,000
Federal share80%
of $665.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du Nord-de-l'Île-de-Montréal
- Construction start
- Nov 1, 2021(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Sep 1, 2021
- Construction end17 months lateforecast Jul 30, 2022
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59267 in the federal list. How to read these figures.