Air conditioning and ventilation units refurbishment at the Hôpital en Santé Mentale Albert Prévost

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$1.5M
$1,456,091
Federal share80%

of $1.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 24, 2023(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start11 months lateforecast Jun 1, 2022
  • Construction end7 months lateforecast Jun 1, 2023

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59269 in the federal list. How to read these figures.