Back to projects

Upgrade of ventilation and air conditioning systems - CHSLD Paul-Gouin

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$500,000
Federal share80%

of $625.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
202220232024
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Sep 29, 2022(actual)
Construction end
Dec 31, 2023(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Sep 1, 2022
  • Construction end4 months lateforecast Sep 1, 2023

Also in Montréal