Upgrade of ventilation and air conditioning systems - CHSLD Paul-Gouin
Federal contribution
$500,000
Federal share80%
of $625.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
202220232024
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du Nord-de-l'Île-de-Montréal
- Construction start
- Sep 29, 2022(actual)
- Construction end
- Dec 31, 2023(actual)
Against the original forecast
- Construction start4 weeks lateforecast Sep 1, 2022
- Construction end4 months lateforecast Sep 1, 2023