Upgrade of ventilation and air conditioning systems - CHSLD Cartierville.

Montréal, Quebec

completeVentilationCVRIS
Federal contribution
$640,000
Federal share80%

of $800.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
20222023
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Jan 26, 2023(actual)
Construction end
Mar 29, 2023(actual)

Against the original forecast

  • Construction start3 months lateforecast Oct 25, 2022
  • Construction end15 months earlyforecast Jun 28, 2024