Roof pond repair work
Federal contribution
$960,000
Federal share58%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 7, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Centre intégré universitaire de santé et de services sociaux du Centre-Ouest-de-l'Île-de-Montréal
- Construction start
- Sep 9, 2021(actual)
- Construction end
- Apr 25, 2022(actual)
Against the original forecast
- Construction start3 months lateforecast Jun 21, 2021
- Construction end5 months lateforecast Nov 30, 2021
Also in Montréal