Back to projects

Upgrading elevators in Mont-Sinai and Henri-Bradet

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$916,268
Federal share76%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 26, 2021(actual)
Construction end
May 31, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Mar 8, 2022

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59277 in the federal list. How to read these figures.