Replacement of boilers
Federal contribution
$975,887
Federal share69%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
2022
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université Concordia
- Construction start
- May 31, 2021(actual)
- Construction end
- Feb 22, 2022(actual)
Against the original forecast
- Construction end2 months lateforecast Dec 18, 2021