Interior renovations at Pavilion AD (Phase 3)
Federal contribution
$2.5M
$2,538,392
Federal share80%
of $3.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 8, 2021
20222023
Built
Approved 4 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Université Concordia
- Construction start
- Aug 9, 2021(actual)
- Construction end
- Dec 22, 2022(actual)
Against the original forecast
- Construction end6 weeks earlyforecast Jan 30, 2023
Also in Montréal
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59280 in the federal list. How to read these figures.