Installation of a toilet and upgrading to universal access and for disabled people on dialysis and the respiratory unit

Montréal, Quebec

completeHealthcare InfrastructureCVRIS
Federal contribution
$20,800
Federal share55%

of $37.6K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 7, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Apr 12, 2021(actual)
Construction end
Apr 1, 2022(actual)

Against the original forecast

  • Construction end3 months lateforecast Dec 31, 2021