Village of Muenster - Interior COVID Renovation Muenster Curling Club

Muenster, Saskatchewan

completeVentilationCVRIS
Federal contribution
$42,424
Federal share40%

of $106.1K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 6, 2021
20222023
Built

Approved 2 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Village of Muenster
Construction start
Jun 10, 2022(actual)
Construction end
Feb 1, 2023(actual)

Against the original forecast

  • Construction start2 months lateforecast Apr 1, 2022
  • Construction end5 weeks lateforecast Dec 31, 2022