Village of Muenster - Interior COVID Renovation Muenster Curling Club
Federal contribution
$42,424
Federal share40%
of $106.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 6, 2021
20222023
Built
Approved 2 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Muenster
- Construction start
- Jun 10, 2022(actual)
- Construction end
- Feb 1, 2023(actual)
Against the original forecast
- Construction start2 months lateforecast Apr 1, 2022
- Construction end5 weeks lateforecast Dec 31, 2022