New Drinking Water Reservoir

Muenster, Saskatchewan

completeDrinking WaterCWWF
Federal contribution
$200,000
Federal share50%

of $400.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 2, 2017
20182019
Built

Approved 6 weeks before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Village of Muenster
Construction start
Aug 8, 2017(actual)
Construction end
Dec 14, 2018(actual)

Against the original forecast

  • Construction start5 weeks lateforecast Jul 1, 2017
  • Construction end2 weeks earlyforecast Dec 31, 2018