New Drinking Water Reservoir
Federal contribution
$200,000
Federal share50%
of $400.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 2, 2017
20182019
Built
Approved 6 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Village of Muenster
- Construction start
- Aug 8, 2017(actual)
- Construction end
- Dec 14, 2018(actual)
Against the original forecast
- Construction start5 weeks lateforecast Jul 1, 2017
- Construction end2 weeks earlyforecast Dec 31, 2018
Also in Muenster
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 50068 in the federal list. How to read these figures.