Back to projects

Envelope Restoration (1 and 2 of 3) of the Strathcona Music Building

Montréal, Quebec

completeEducation, Training and ChildcareCVRIS
Federal contribution
$2.6M
$2,631,814
Federal share61%

of $4.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 8, 2021
2022
Built

Approved 4 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
McGill University
Construction start
Jun 18, 2021(actual)
Construction end
Aug 26, 2022(actual)

Also in Montréal

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59351 in the federal list. How to read these figures.