Ste. Agathe Red River Access

Ritchot, Manitoba

completeRecreationRNIS
Federal contribution
$110,206
Federal share40%

of $275.5K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 31, 2022
20222023
Built

Approved 16 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Sep 14, 2021(actual)
Construction end
Mar 29, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Aug 1, 2021
  • Construction end3 months lateforecast Dec 31, 2022

Also in Ritchot

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59352 in the federal list. How to read these figures.