Ste. Agathe Red River Access
Federal contribution
$110,206
Federal share40%
of $275.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 31, 2022
20222023
Built
Approved 16 months before the announcement.
- Program
- Rural & Northern Infrastructure Stream
- Ultimate recipient
- Ste. Agathe Community Development Incorporate
- Construction start
- Sep 14, 2021(actual)
- Construction end
- Mar 29, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Aug 1, 2021
- Construction end3 months lateforecast Dec 31, 2022
Also in Ritchot