Grande Pointe Community Clubhouse

Ritchot, Manitoba

completeCultureRNIS
Federal contribution
$101,699
Federal share40%

of $254.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2021
Built

Approved 3 months before the announcement.

Program
Rural & Northern Infrastructure Stream
Construction start
Jun 23, 2021(actual)
Construction end
Nov 30, 2021(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 1, 2021