Frontenac Admin Reception Redesign
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
202220232024
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- County of Frontenac
- Construction start
- Jul 15, 2022(actual)
- Construction end
- Dec 22, 2023(actual)
Against the original forecast
- Construction end3 weeks lateforecast Dec 1, 2023