Fairmount HVAC Equipment

Frontenac, Ontario

completeVentilationCVRIS
Federal contribution
$941,824
Federal share80%

of $1.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 16, 2021
20222023
Built

Approved 4 weeks before the announcement.

Program
COVID-19 Resilience Stream
Construction start
Oct 24, 2022(actual)
Construction end
Feb 28, 2023(actual)

Against the original forecast

  • Construction start10 months lateforecast Jan 4, 2022
  • Construction end4 weeks earlyforecast Mar 31, 2023