Back to projects

Construction of Multi-Use Pathway-Laurentian Drive

Petawawa, Ontario

completeActive TransportationCVRIS
Federal contribution
$80,000
Federal share80%

of $100.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJun 15, 2021
Built

Approved 3 months before the announcement.

Program
COVID-19 Resilience Stream
Ultimate recipient
Town of Petawawa
Construction start
Jun 30, 2021(actual)
Construction end
Oct 14, 2021(actual)

Against the original forecast

  • Construction start4 weeks lateforecast Jun 1, 2021
  • Construction end7 weeks earlyforecast Nov 30, 2021