Construction of Multi-Use Pathway-Laurentian Drive
Federal contribution
$80,000
Federal share80%
of $100.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJun 15, 2021
Built
Approved 3 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Town of Petawawa
- Construction start
- Jun 30, 2021(actual)
- Construction end
- Oct 14, 2021(actual)
Against the original forecast
- Construction start4 weeks lateforecast Jun 1, 2021
- Construction end7 weeks earlyforecast Nov 30, 2021
Also in Petawawa
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 59373 in the federal list. How to read these figures.